Wind Farm Construction: Onshore and Offshore Wind Project Construction with Substantial Logistics
Wind farm construction involves substantial logistics for tower foundations, turbine assembly, electrical infrastructure, and grid interconnection. Onshore wind dominant US market with substantial Plains and Texas concentration. Offshore wind emerging substantially particularly Northeast US with substantial federal and state policy support. Components include massive concrete foundations, substantial tower segments, nacelles (housing generators), blades, and grid infrastructure. Specialty contractors and equipment (substantial cranes) essential. Understanding wind farm construction helps GCs evaluate this growing renewable specialty.
This post covers wind farm construction.
Onshore wind components:
Onshore wind
- Substantial concrete foundations (1000+ cy each)
- Tower segments (3-5 typically, 250-500 feet high)
- Nacelle (substantial weight, 50-200+ tons)
- Blades (180+ feet long typical)
- Substantial cranes for assembly
- Underground collection cables
- Substation
- Specific to turbine size
Onshore wind substantial components. Substantial concrete foundations 1000+ cubic yards each — substantial concrete operation. Tower segments 3-5 typically, 250-500 feet high. Nacelle (housing generator) substantial weight 50-200+ tons depending on turbine. Blades 180+ feet long typical (substantial transportation challenge). Substantial cranes for assembly (one of largest land-based cranes used). Underground collection cables connecting turbines. Substation for grid interconnection. Specific to turbine size which has grown substantially.
Foundations substantial:
Foundations
- Spread footings (most common)
- Pile foundations (challenging soils)
- 1000+ cubic yards concrete each
- Substantial reinforcement
- Specific to turbine and soil
- Engineering substantial
Foundations substantial wind farm component. Spread footings most common (substantial concrete pad). Pile foundations for challenging soils. 1000+ cubic yards concrete each — substantial concrete operation per turbine. Substantial reinforcement design. Specific to turbine size and soil conditions. Engineering substantial — dynamic loads from turbine operation, wind loads.
Logistics substantial:
Turbine logistics
- Tower segments (substantial vehicles)
- Blade transport (180+ feet long)
- Specific route planning
- Permits for oversized loads
- Substantial mobilization
- Specific to project size
- Often substantial transportation cost
Logistics substantial in wind farm construction. Tower segments require substantial vehicles for transport. Blade transport 180+ feet long substantial challenge. Specific route planning addressing turns, low-clearance bridges, narrow roads. Permits for oversized loads. Substantial mobilization to remote sites typical. Specific to project size. Often substantial transportation cost — sometimes 10%+ of project cost.
Specialty cranes substantial:
Specialty cranes
- Massive lattice boom cranes
- 1000+ ton capacity typical
- 300-400+ feet reach
- Specialty rigging contractors
- Substantial cost per project
- Schedule sensitive (weather)
- Specific to turbine height
Specialty cranes substantial wind farm requirement. Massive lattice boom cranes — some of largest land-based. 1000+ ton capacity typical for substantial turbines. 300-400+ feet reach for tall towers. Specialty rigging contractors operating cranes. Substantial cost per project. Schedule sensitive — wind speed limits crane operation. Specific to turbine height which continues growing.
Get AP insights in your inbox
A short monthly roundup of construction AP + accounting posts. No spam, ever.
No spam. Unsubscribe anytime.
Offshore wind substantial different:
Offshore wind
- Marine construction substantially
- Specialty installation vessels
- Substantial larger turbines (8-15+ MW)
- Foundations (monopile, jacket, floating)
- Substantial cost premium vs onshore
- Substantial federal/state support
- US emerging market
Offshore wind substantially different from onshore. Marine construction substantially affecting all aspects. Specialty installation vessels (Wind Turbine Installation Vessels — WTIVs) for installation. Substantial larger turbines 8-15+ MW (vs 2-5 MW onshore typical). Foundations include monopile (single substantial pile), jacket (lattice structure), floating for deep water. Substantial cost premium vs onshore (offshore 2-3x onshore per MW). Substantial federal and state support including Inflation Reduction Act. US emerging market with substantial Northeast development.
Grid interconnection substantial:
Grid interconnection
- Collection system (medium voltage)
- Substation transforms
- Transmission interconnection
- Specific FERC and state coordination
- Substantial transmission upgrades sometimes
- Critical path typically
Grid interconnection substantial wind farm component. Collection system at medium voltage from turbines. Substation transforms to transmission voltage. Transmission interconnection to grid. Specific FERC and state coordination throughout. Substantial transmission upgrades sometimes required at developer cost. Critical path typically for project timing.
Wind farm construction substantial market opportunity from energy transition. Onshore wind mature market with established contractors; offshore wind emerging in US. Specialty equipment (cranes, vessels) and expertise essential. Logistics challenges substantial. Quality wind-experienced contractors with proven safety records and productivity differentiate. Worth substantial expertise development for firms pursuing.
Specialty contractors dominate:
Specialty contractors
- Major wind EPCs (Blattner, Mortenson, Bechtel)
- Specialty erection contractors
- Specialty rigging companies
- Specific to scope
- Substantial industry
Specialty contractors dominate wind farm construction. Major wind EPCs include Blattner Energy, Mortenson, Bechtel, others substantial wind portfolios. Specialty erection contractors handling turbine assembly. Specialty rigging companies with substantial cranes. Specific to scope. Substantial industry with established players and ongoing competition.
Wind farm construction onshore and offshore renewable specialty. Onshore wind components include foundations, towers, nacelles, blades, cranes, electrical, substation. Foundations substantial concrete operation. Turbine logistics substantial challenge with oversized loads. Specialty cranes substantial requirement. Offshore wind substantially different with marine construction, specialty vessels, substantial costs. Grid interconnection substantial coordination. For GCs pursuing renewable energy, wind farms substantial market opportunity. Specialty contractors dominate. Worth substantial expertise development.
Written by
Marcus Reyes
Construction Industry Lead
Spent twelve years running AP at a $120M general contractor before joining Covinly. Lives in the world of AIA G702/G703, retainage schedules, and lien waiver deadlines. Writes about the construction-specific workflows that generic AP tools get wrong.
View all posts