Georgia Mechanics Lien Deadlines: The Notice to Contractor and the 90-Day Filing Window
Georgia's mechanics lien framework has a distinctive front end: before a subcontractor or supplier worries about the lien-filing deadline, it has to deal with the Notice of Commencement and the Notice to Contractor. Whether the property owner recorded a Notice of Commencement, and when, drives a 30-day Notice to Contractor deadline that a claimant without a direct contract with the general contractor must meet — and failing to meet it eliminates the lien right before the claimant ever reaches the 90-day filing window.
The governing law is found in the Official Code of Georgia Annotated, Title 44, Chapter 14, Article 8, Part 3 — the materialmen's and mechanics' lien provisions, principally O.C.G.A. § 44-14-361 and § 44-14-361.1. Georgia courts construe these lien statutes strictly against the claimant, and the procedure has more moving parts than a simple file-and-foreclose sequence: there is a pre-lien notice tied to the Notice of Commencement, a filing deadline, an enforcement-suit deadline, and a separate notice that must be filed in the property's county after suit is brought. This guide covers private-project liens; verify the current Code text before relying on any specific deadline.
Georgia's lien statutes extend rights broadly, and the key procedural divide is privity with the general contractor:
Georgia mechanics lien claimants
- General contractor — in direct contract with the owner; does not serve a Notice to Contractor, since it is the contractor
- Subcontractor — in contract with the general contractor; in privity with the GC, with its own notice considerations
- Sub-subcontractor and lower tiers — without privity of contract with the general contractor; must serve a Notice to Contractor to preserve lien rights when a Notice of Commencement was filed
- Material suppliers — without privity with the general contractor; subject to the Notice to Contractor requirement on the same terms
- Design professionals (architects, engineers, surveyors) and certain others — covered, with their own qualifying conditions
The phrase to watch in Georgia is without privity of contract with the contractor. A claimant in that position — typically a sub-subcontractor or a supplier to a subcontractor — is the one for whom the Notice to Contractor is a hard, lien-preserving requirement.
Georgia's preliminary-notice mechanism is a two-document interaction. The Notice of Commencement is recorded by or on behalf of the owner or general contractor near the start of the project; it identifies the project, the owner, the contractor, and a point of contact, and it is filed with the clerk of the superior court and posted at the site.
The Notice of Commencement triggers the claimant's obligation. A potential lien claimant without privity of contract with the general contractor must give a written Notice to Contractor within 30 days of the filing of the Notice of Commencement, or within 30 days of first furnishing labor, services, or materials to the property — whichever is later. The Notice to Contractor goes to the owner (or its agent) and the general contractor, and it must be served by a statutorily reliable method — certified mail, registered mail, or statutory overnight delivery — with proof of receipt.
In Georgia, if a Notice of Commencement was filed and a claimant without privity with the general contractor fails to serve the Notice to Contractor within the statutory window, the lien right is eliminated — the claimant cannot file a valid lien at all. This is a true gate. Before doing anything else on a Georgia project, a sub-subcontractor or supplier should search for a recorded Notice of Commencement and check the site posting, because its filing date starts a 30-day clock.
The interaction with the Notice of Commencement is the part that catches claimants. If the owner files a Notice of Commencement and the claimant does not see it, the 30-day clock can run from a filing the claimant never knew about — measured from the later of that filing or first furnishing. The defensive move is simple and should be routine: check for a Notice of Commencement at the start of every Georgia job and serve a Notice to Contractor whenever one exists and the claimant lacks privity with the GC.
The core payload is the lien claim, and the deadline is short. A claim of lien must be filed within 90 days after the claimant last furnished labor, services, or materials to the project. Georgia frames this as roughly a three-month window from last furnishing, and a claim of lien filed after it is invalid regardless of the merit of the underlying debt.
The 90-day clock runs from the last substantive furnishing. As elsewhere, punch list, warranty, and minor remedial work generally do not extend the date, so a claimant who treats a late corrective visit as a fresh trigger can file a claim of lien that is, in fact, weeks late. The claim of lien must also state the claimed amount, and the aggregate of all liens on the project generally cannot exceed the contract price of the improvements — an overstated lien is exposed to challenge.
Georgia also requires the claimant to send a copy of the filed claim of lien to the owner and, where applicable, the contractor within a short statutory window of filing. Treat sending that copy as part of the filing task.
The claim of lien is filed with the clerk of the superior court of the county where the property is located, in the county lien records. The claim must contain the statutorily required content: the claimant's name and the amount claimed; the name of the owner; identification of the property sufficient for it to be located; the name of the party with whom the claimant contracted; the dates of furnishing; and the statutorily prescribed notice language that Georgia requires the claim to include for the owner's benefit.
Georgia's lien form requirements are specific — the statute prescribes cautionary language that must appear in the claim. A claim of lien that omits required content can be challenged on that basis, so the form should track the current statutory template.
Georgia mechanics liens generally relate back to the commencement of the work for priority purposes, so liens for an improvement share a common relation-back point rather than ranking by the date each individual claimant happened to start. Against that backdrop, the timing of a construction lender's security deed relative to the start of visible work governs whether the lender's interest is ahead of or behind the mechanics liens.
The aggregate-cap rule also shapes priority in practice: because the total of all liens on a project cannot exceed the contract price of the improvements, a project with many claimants can find the available lien amount fully subscribed, which makes prompt and accurate filing matter even more.
Get AP insights in your inbox
A short monthly roundup of construction AP + accounting posts. No spam, ever.
No spam. Unsubscribe anytime.
The Owner's Notice of Contest and Bonding Off
Georgia gives the owner, the general contractor, or another authorized party a tool to compress the claimant's enforcement timeline: the Notice of Contest of Lien. When a valid Notice of Contest of Lien is filed and received by the claimant, the lien expires a set period after the claimant receives it unless the claimant commences a lien action within the statutory window measured from when the lien was recorded. A claimant served with a Notice of Contest cannot safely assume the full default enforcement period still applies.
Georgia also allows a lien to be discharged from the property by filing a bond. The lien is released from the real estate and the claimant's recourse shifts to the bond — title is cleared while the claimant's right to be paid is preserved against the security. A claimant whose lien has been bonded off should confirm how the bond changes the parties and the enforcement mechanics for its claim.
Filing the claim of lien preserves the lien; Georgia then requires two further steps to enforce it, and both have deadlines. First, the claimant must commence a lien action to recover the amount of the claim within 365 days of the date the claim of lien was filed. Failing to bring suit within that year renders the lien unenforceable.
Second — and this step is unique enough that out-of-state contractors miss it — the claimant must file a Notice of Commencement of Lien Action with the clerk of the superior court of the county where the property is located, within 30 days after commencing the lien action. A claimant who files suit on time but fails to file that separate notice in the county records within the 30 days can still lose the lien. In effect, Georgia requires the claimant both to sue within 365 days and to record notice of that suit within a further 30 days. A foreclosure action proceeds in court and, if the claimant prevails, results in a judgment; in practice most Georgia lien claims resolve through payment to clear title rather than at a sale.
Georgia prescribes statutory lien-waiver forms, and it pairs them with a rule that has bitten many claimants. The statute sets out interim and final waiver-and-release forms, and a waiver should track the statutory form to be effective. The rule to know is the one tied to time: under Georgia's lien statute, a lien waiver historically becomes binding and conclusive on the claimant after a statutory period passes from the date stated on the waiver, unless within that period the claimant files an affidavit of nonpayment (or files its lien). Verify the current waiver provisions and the applicable period, because they have been amended.
The practical effect: in Georgia a claimant can sign an interim waiver expecting payment, never receive the money, and still have the waiver harden against it by operation of the statutory clock unless it acts within the window. A claimant who has signed a waiver and not been paid must watch that period and file an affidavit of nonpayment (or its lien) before the clock runs. As always, an unconditional or final waiver should be exchanged only against cleared funds.
For a Georgia subcontractor or supplier — particularly one without privity with the general contractor — the workable sequence is:
Georgia mechanics lien timing strategy
- At the start of the job, search for a recorded Notice of Commencement and check the site posting
- If a Notice of Commencement exists and the claimant lacks privity with the GC, serve a Notice to Contractor within 30 days of the later of that filing or first furnishing — by certified mail, registered mail, or statutory overnight delivery, with proof of receipt
- Document the last date of furnishing carefully — punch list and warranty work generally do not extend it
- File the claim of lien with the superior court clerk within 90 days of last furnishing, using the statutory form and language
- Send the filed claim of lien copy to the owner and contractor within the statutory window
- If a signed interim waiver is outstanding and payment has not arrived, file an affidavit of nonpayment (or the lien) before the statutory waiver period runs
- Commence the lien action within 365 days of filing the claim of lien, then file the Notice of Commencement of Lien Action with the superior court clerk within 30 days of commencing suit
Georgia front-loads and back-loads procedural traps. At the front, a recorded Notice of Commencement starts a 30-day Notice to Contractor clock that gates lien rights entirely. At the back, enforcing the lien takes both a lawsuit within 365 days and a separately filed Notice of Commencement of Lien Action within 30 days of suit. Miss either bookend and an otherwise valid lien fails. Treat the Notice of Commencement search as step one of every Georgia job.
Georgia's mechanics lien framework under O.C.G.A. Title 44 turns on procedure as much as deadlines. If the owner recorded a Notice of Commencement, a claimant without privity with the general contractor must serve a Notice to Contractor within 30 days of the later of that filing or first furnishing — and missing it eliminates the lien right entirely. The claim of lien must then be filed with the superior court clerk within 90 days of last furnishing. Enforcement requires both a lien action within 365 days of filing the claim and a separately filed Notice of Commencement of Lien Action within 30 days of commencing suit. Statutory waiver forms apply, and a Georgia lien waiver can harden against an unpaid claimant by operation of a statutory clock unless the claimant files an affidavit of nonpayment in time. Because the procedure has more steps than most states' and Georgia construes the statutes strictly, verify the current Code requirements against the project's facts. For significant claims, experienced Georgia construction counsel is a worthwhile investment.
Written by
Jordan Patel
Compliance & Legal
Former corporate counsel specializing in construction contracts and tax compliance. Writes about the documentation layer — COIs, W-8/W-9, certified payroll, notice-to-owner deadlines — and the legal backbone behind audit-ready AP.
View all posts