Construction Claim Preparation: Documentation, Causation, Damages, and Quality Claim Submission
Construction claims pursue compensation for delays, changes, differing site conditions, and other compensable events under contract. Quality claim preparation requires comprehensive documentation, causation analysis (showing what caused damages), and damage calculation (quantifying loss). Poor claim preparation produces denied claims even when contractors have valid entitlements. Substantial claims often require specialty consultants (scheduling, cost). Understanding claim preparation helps construction firms pursue legitimate claims effectively.
This post covers construction claim preparation.
Common claim categories:
Claim categories
- Delay claims
- Differing site conditions
- Changes (constructive, formal)
- Suspension of work
- Termination
- Lost productivity (impact)
- Acceleration
- Specific to circumstances
Common claim categories in construction. Delay claims for excusable, compensable delays. Differing site conditions when actual differs materially from contract conditions. Changes including constructive (owner conduct creating change) and formal change orders. Suspension of work when owner suspends. Termination claims (convenience or default). Lost productivity (impact) from disruption. Acceleration when owner directs faster work. Specific to circumstances.
Documentation foundation:
Documentation
- Daily reports (substantial value)
- RFIs and responses
- Photos with dates
- Schedule updates
- Cost tracking
- Communications (emails, letters)
- Time-impact analyses
- Specific to claim type
Documentation foundation of claims. Daily reports substantial value — contemporaneous records of conditions, work, weather, manpower. RFIs and responses showing communication history. Photos with dates documenting site conditions. Schedule updates showing impact progression. Cost tracking by activity. Communications including emails, letters showing notification, response. Time-impact analyses by scheduling experts. Specific to claim type — different claims emphasize different documentation.
Causation links event to damages:
Causation
- Event identification (what happened)
- Notice provided (timely)
- Impact on critical path (delay)
- Cause and effect demonstrated
- Specific causation analysis
- Concurrent delay considerations
- Specific to claim
Causation links event to damages — essential for claim entitlement. Event identification showing what happened. Notice provided timely per contract requirements (often within days of event). Impact on critical path for delay claims. Cause and effect demonstrated through analysis. Specific causation analysis (cumulative impact, time-impact analysis). Concurrent delay considerations — when contractor and owner both caused delay, recovery limited. Specific to claim.
Damages quantify loss:
Damages
- Direct costs (labor, materials, equipment)
- Extended general conditions (time-related)
- Home office overhead (Eichleay sometimes)
- Lost productivity (measured mile, etc.)
- Acceleration costs
- Bond premium increases
- Profit on direct costs
- Specific cost methodology
Damages quantify financial loss. Direct costs including labor, materials, equipment for affected work. Extended general conditions (time-related costs) for delay periods. Home office overhead through Eichleay formula sometimes. Lost productivity calculated through measured mile or other methodologies. Acceleration costs (overtime, premium time, additional crews). Bond premium increases. Profit on direct costs typical. Specific cost methodology supporting calculation.
Get AP insights in your inbox
A short monthly roundup of construction AP + accounting posts. No spam, ever.
No spam. Unsubscribe anytime.
Schedule analysis for delay claims:
Schedule analysis
- As-planned schedule (baseline)
- As-built schedule (actual)
- Time-impact analysis
- Window analysis
- Specific methodology per circumstances
- Critical path impact
- AACE recommended practices
Schedule analysis for delay claims. As-planned schedule (baseline) shows contracted plan. As-built schedule (actual) shows what occurred. Time-impact analysis (TIA) inserts delay events into schedule and measures impact. Window analysis evaluates specific periods. Specific methodology per circumstances. Critical path impact required for compensable delay (off-critical delays don't extend completion). AACE recommended practices guide methodologies.
Notice requirements substantial:
Notice requirements
- Specific contract notice provisions
- Often 7-14 days from event
- Written notice typical
- Failure to provide may bar claim
- Substantial enforcement of notice
- Specific to contract
- Document promptly
Notice requirements substantial under most contracts. Specific contract notice provisions per contract. Often 7-14 days from event for written notice. Written notice typical via specific format or letter. Failure to provide notice may bar claim entirely — substantial defense by owners. Substantial enforcement of notice in modern construction — owners increasingly strict. Specific to contract terms. Document promptly when events occur preserving claim rights.
Construction claim preparation quality substantially affects recovery — well-prepared claims with comprehensive documentation, clear causation, and quantified damages typically settle favorably. Poorly prepared claims with weak documentation often denied even with valid entitlement. Quality claim preparation often requires specialty consultants (scheduling, cost) for substantial claims — cost typically justified by recovery improvement.
Resolution paths:
Settlement vs litigation
- Direct negotiation (preferred)
- Mediation (assisted negotiation)
- Arbitration (binding)
- Litigation (court)
- Specific to contract dispute resolution
- Cost vs recovery analysis
- Most claims settle
Resolution paths from negotiation through litigation. Direct negotiation preferred path — lowest cost, faster, preserves relationships. Mediation provides neutral facilitator. Arbitration binding through arbitrator decision. Litigation in court last resort. Specific to contract dispute resolution provisions. Cost vs recovery analysis determines escalation — substantial cost may exceed recovery for smaller claims. Most claims settle through negotiation or mediation — small percentage proceed to arbitration or litigation.
Construction claim preparation requires documentation, causation analysis, and damage calculation. Common claim categories include delay, differing site conditions, changes, lost productivity. Documentation foundation includes daily reports, RFIs, photos, schedule updates, cost tracking. Causation links event to damages. Damages quantify loss through direct costs, extended general conditions, lost productivity. Schedule analysis essential for delay claims. Notice requirements substantial — failure to provide may bar claims. Resolution through negotiation, mediation, arbitration, or litigation. For construction firms, quality claim preparation substantially affects recovery. Specialty consultants justify cost for substantial claims. Claim preparation is essential capability for construction risk management and disputes.
Written by
Jordan Patel
Compliance & Legal
Former corporate counsel specializing in construction contracts and tax compliance. Writes about the documentation layer — COIs, W-8/W-9, certified payroll, notice-to-owner deadlines — and the legal backbone behind audit-ready AP.
View all posts